Project Update: April 17, 2023
04.17.2023
Next week, barring inclement weather, you can expect to see continued excavation and duct bank installation at our work sites on Furnace Brook Parkway and Newport Avenue as well as test pit excavation on a portion of Southern Artery.
In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections between 259 and 529 Newport Avenue as well as 3 and 19 Newport Terrace. This work will begin as night work on Newport Avenue between Brook Street and Beale Street. Following weeks of night work will be between 7:00PM and 5:00AM, Monday through Frisday. As this work progresses, we look forward to providing more information.
As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.
For a closer look at the project route, please click here to view our online map.
Week of April 17: Construction Activity
- Finalizing duct bank installation on Newport Avenue (near 65 Newport Avenue)
- Finalizing duct bank installation on Furnace Brook Parkway (near 400 Newport Avenue)
- Construction at Field Street Substation
- Nighttime main replacement on Newport Avenue between Brook Street and Beale Street
Week of April 24: Construction Activity
- Finalizing duct bank installation on Furnace Brook Parkway (near 400 Newport Avenue)
- Finalizing duct bank installation on Newport Avenue (near 59 Newport Avenue)
- Construction at Field Street Substation
- Nighttime main replacement on Newport Avenue between Brook Street and Beale Street
Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.
For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.
*Please note, due to the complexities of outdoor construction, schedule is subject to change.