Latest Project Updates

03.12.2026

Project Update: Roadway Restoration

Starting the week of March 16, you can expect to see contractor activity on various sections of Newport Avenue and Newport Avenue Extension as we work to complete sidewalk and road restoration between Beale Street and Heritage Drive.

Read more

03.12.2026

Project Update: Roadway Restoration

Starting the week of March 16, you can expect to see contractor activity on various sections of Newport Avenue and Newport Avenue Extension as we work to complete sidewalk and road restoration between Beale Street and Heritage Drive.

Read more

03.07.2025

Project Update: Roadway Restoration

Starting the week of March 17, in coordination with the City of Quincy, we’re planning to repave and restore city streets where we’ve worked over the last two years.

Read more

05.07.2024

Project Update: Cable Removal

Next week you can expect to see crew activity at locations along the project route (Newport Avenue) as contractors remove the pre-existing underground cable adjacent to the North Quincy Cable Project route.

Read more

01.05.2024

Project Update: January 5, 2024

Next week you can expect to see National Grid Gas activity on Newport Avenue between 541 – 627 Newport Avenue. Please note that work hours are 7:00AM to 3:00PM, Monday through Friday.

Read more

12.11.2023

Project Update: December 11, 2023

Next week please expect to see National Grid Gas activity at work sites on Newport Avenue as they work to replace existing mains along the road. Please note that work hours for this area are 7:00AM to 3:00PM, Monday through Friday. Please note that all Quincy Cable Project work is now taking place within substations.

Read more

12.05.2023

Project Update: December 5, 2023

Next week please expect to see National Grid Gas activity at work sites on Newport Avenue as they work to replace existing mains along the road. Please note that work hours for this area are 7:00AM to 3:00PM, Monday through Friday. Please note that all Quincy Cable Project work is now taking place within substations.

Read more

11.27.2023

Project Update; November 27, 2023

This week please expect to see National Grid Gas activity at work sites on Newport Avenue as they work to replace existing mains along the road. Please note that work hours for this area are 7:00AM to 3:00PM, Monday through Friday.

Read more

11.10.2023

Project Update: November 10, 2023

Next week can expect to see National Grid Gas activity at work sites on Newport Avenue as they work to replace existing mains along the road. Please note that work hours for this area are 7:00AM to 3:00PM, Monday through Friday.

Read more

10.27.2023

Project Update: October 27, 2023

As part of our ongoing commitment to keeping you informed, we'd like to provide an update on the construction activities for the North Quincy Cable Project.

Read more