Latest Project Updates

09.11.2023

Project Update: September 11, 2023

This week can expect to see continued construction activity at work sites on Furnace Brook Parkway, Southern Artery, and Newport Avenue. You may also notice intermittent work at various locations along the project route. Please note that contractors are utilizing nights and Saturdays to extend the work week and expedite construction.

Read more

09.01.2023

Project Update: September 1, 2023

Next week can expect to see continued construction activity at work sites on Furnace Brook Parkway, Southern Artery, and Newport Avenue. You may also notice intermittent work at various locations along the project route. Please note that contractors are utilizing nights and Saturdays to extend the work week and expedite construction.

In addition to duct bank installation for the North Quincy Cable Project, as of Tuesday, August 22, National Grid Gas began working at night for approximately two weeks. This work will be in the area of Beale Street and Newport Avenue as well as Willow Avenue and Newport Avenue.

Read more

07.17.2023

Project Update: July 14, 2023

Next week, you can expect to see continued construction activity at work sites on Furnace Brook Parkway, Southern Artery, Newport Avenue, and within the North Quincy Substation. You may also notice intermittent work at various locations along the project route. Please note that contractors are utilizing Saturdays to extend the work week and expedite construction.

In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections on Newport Avenue. This work is switching back to daytime work on Newport Avenue between Brook Street to Willow Avenue.

Read more

06.05.2023

Project Update: June 2, 2023

Next week can expect to see continued construction activity at our work sites on Furnace Brook Parkway, Southern Artery, Field Street Substation You may also notice intermittent work at various locations along the project route.

In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections on Newport Avenue. This work is taking place on Newport Avenue between Cedar Street and Furnace Brook Parkway.

Read more

05.30.2023

Project Update: May 30, 2023

Next week can expect to see continued construction activity at our work sites on Furnace Brook Parkway, Southern Artery, Field Street Substation You may also notice intermittent work at various locations along the project route.

In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections on Newport Avenue. This work is taking place on Newport Avenue between Cedar Street and Furnace Brook Parkway.

Read more

05.23.2023

Project Update: May 19, 2023

Next week you can expect to see continued construction activity at our work sites on Furnace Brook Parkway, Southern Artery, Field Street Substation You may also notice intermittent work at various locations along the project route.

Read more

05.08.2023

Project Update: May 5, 2023

Next week can expect to see construction activity at our work sites on Furnace Brook Parkway, Newport Avenue, Field Street Substation and Southern Artery. You may also notice intermittent work at various locations along the project route.

Read more

05.01.2023

Project Update: April 28, 2023

For the next two weeks, you can expect to see construction activity at our work sites on Furnace Brook Parkway, Newport Avenue, Field Street Substation and Southern Artery.

Read more

04.21.2023

Project Update: April 21, 2023

Next week, barring inclement weather, you can expect to see continued excavation and duct bank installation at our work sites on Furnace Brook Parkway, Newport Avenue, Field Street Substation. In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections on Newport Avenue.

Read more

04.17.2023

Project Update: April 17, 2023

Next week, barring inclement weather, you can expect to see continued excavation and duct bank installation at our work sites on Furnace Brook Parkway and Newport Avenue as well as test pit excavation on a portion of Southern Artery.

Read more