Project Update: February 3, 2023
02.03.2023
Next week duct bank excavation and installation continues at our work sites on Furnace Brook Parkway and Field Street / Morrison Street. Please note that as construction progresses onto the eastern end of Morrison Street, the western end of the street will remain accessible for businesses and residents.
As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.
For a closer look at the project route, please click here to view our online map.
Week of February 6: Construction Activity
- Duct bank installation near the intersection of Field Street and Morrison Street
- Duct bank installation on Furnace Brook Parkway between Hancock Street and Lafayette Street
Week of February 13: Construction Activity
- Duct bank installation near the intersection of Field Street and Morrison Street
- Duct bank installation on Furnace Brook Parkway between Hancock Street and Putnam Street.
Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.
For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.
*Please note, due to the complexities of outdoor construction, schedule is subject to change.