Project Update: May 19, 2023

Project Update: May 19, 2023

05.23.2023

Next week you can expect to see continued construction activity at our work sites on Furnace Brook Parkway, Southern Artery, Field Street Substation You may also notice intermittent work at various locations along the project route.

In addition to duct bank installation for the North Quincy Cable Project, National Grid Gas is also replacing existing gas mains and connections on Newport Avenue. This work is taking place on Newport Avenue south of Beale Street and Willow Street.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of May 22: Construction Activity

  • Duct bank installation near 325 Southern Artery
  • Duct bank installation near 235 Southern Artery
  • Duct bank installation on Furnace Brook Parkway between Hancock Street and Newport Avenue
  • Construction at Field Street Substation
  • Main replacement on Newport Avenue between Beale Street and Willow Street


Week of May 29: Construction Activity

  • Duct bank installation near 325 Southern Artery
  • Duct bank installation near 235 Southern Artery
  • Duct bank installation on Furnace Brook Parkway between Hancock Street and Newport Avenue
  • Construction at Field Street Substation
  • Main replacement on Newport Avenue between Beale Street and Willow Street


Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.