Project Update: November 4, 2022

Project Update: November 4, 2022

11.04.2022

Next week you can expect to see construction activity at two main work sites on Newport Avenue (between Beale Street and Brook Avenue and between Hobart Street and Holbrook Road).

As previously mentioned, the work taking place on Newport Avenue in the area of Beale Street and Brook Street requires an overnight work schedule per the direction of local safety officials. Construction hours at this work site are 7:30pm to 5:30am, Sunday evening to Friday morning. We look forward to completing work on this part of the route in the coming weeks.

Our daytime crew will continue duct bank installation on Newport Avenue between Hobart Street and Holbrook Road. Construction hours at this work site are 7:00am to 4:30pm, Monday through Friday.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of November 7: Construction Activity

  1. Night Work (Sunday to Friday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between Hobart Street and Holbrook Road


Week of November 14: Construction Activity

  1. Duct bank installation on Newport Avenue between Hobart Street and Holbrook Road
  2. Duct bank installation on Newport Avenue between Newport Terrace and Warren Avenue
  3. Handhole installation on Newport Avenue between Lincoln Avenue and Warren Avenue


Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.

*Please note, due to the complexities of outdoor construction, schedule is subject to change.