Project Update: October 14, 2022

Project Update: October 14, 2022

10.17.2022

During the week of October 17, you can expect to see construction activity at two main work sites on Newport Avenue (between Beale Street and Brook Avenue and between N. Central Avenue and Hobart Street).

As previously mentioned, the work taking place on Newport Avenue in the area of Beale Street and Brook Street requires an overnight work schedule per the direction of local safety officials. Construction hours at this work site are 7:30pm to 5:30am, Sunday evening to Friday morning.

Regular construction daytime hours will continue to be in place at our other work site on Newport Avenue (between N. Central Avenue and Hobart Street). This crew will progress in the direction of Wilson Avenue in the coming weeks.

At both work sites, crews will continue excavating and installing duct bank to connect previously installed manholes on Newport Avenue.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of October 17: Construction Activity

  1. Night Work (Sunday to Friday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between N. Central Avenue and Hobart Street


Week of October 24: Construction Activity

  1. Night Work (Sunday to Friday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between N. Central Avenue and Hobart Street


Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.

Thank you,

The North Quincy Cable Project

*Please note, due to the complexities of outdoor construction, schedule is subject to change.