Project Update: October 21, 2022

Project Update: October 21, 2022

10.21.2022

Next week you can expect to see construction activity at three main work sites on Newport Avenue (between Newport Terrace and Warren Avenue, between Beale Street and Brook Avenue and between N. Central Avenue and Wilson Avenue).

As previously mentioned, the work taking place on Newport Avenue in the area of Beale Street and Brook Street requires an overnight work schedule per the direction of local safety officials. Construction hours at this work site are 7:30pm to 5:30am, Sunday evening to Friday morning.

For approximately two weeks, starting during the week of October 24, you can expect to see daytime construction activity on Newport Avenue (between Newport Terrace and Warren Avenue) as contractors complete the installation of underground duct bank on each side of the manhole location on this part of the street.

Regular daytime construction hours will continue to be in place at our other work site on Newport Avenue (between N. Central Avenue and Wilson Avenue). This crew will progress in the direction of Wilson Avenue in the coming weeks.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of October 24: Construction Activity

  1. Night Work (Sunday to Friday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between N. Central Avenue and Wilson Avenue
  3. Duct bank installation on Newport Avenue between Newport Terrace and Warren Avenue


Week of October 31: Construction Activity

  1. Night Work (Sunday to Friday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between N. Central Avenue and Wilson Avenue
  3. Duct bank installation on Newport Avenue between Newport Terrace and Warren Avenue


Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.

Thank you,

The North Quincy Cable Project

*Please note, due to the complexities of outdoor construction, schedule is subject to change.