Next week you can expect to see continued construction activity at two main work sites on Newport Avenue (between Willow Avenue and Lillian Road and between Beale Street and Brook Avenue).

At both work sites, crews will continue excavating and installing duct bank to connect previously installed manholes on Newport Avenue.

Please note that the work taking place on Newport Avenue in the area of Beale Street and Brook Street requires an overnight work schedule per the direction of local safety officials. Construction hours at this work site are 7:30pm to 5:30am, Monday through Thursday.

Regular construction daytime hours will continue to be in place at our other work site on Newport Avenue.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of September 26: Construction Activity

  1. Night Work (Monday-Thursday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between Willow Avenue and Lillian Road


Week of October 3: Construction Activity

  1. Night Work (Sunday-Thursday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Beale Street and Brook Street
  2. Duct bank installation on Newport Avenue between Willow Avenue and Lillian Road


Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.

*Please note, due to the complexities of outdoor construction, schedule is subject to change.