Project Update: September 2, 2022

Project Update: September 2, 2022

09.02.2022

This week you can expect to see continued activity at two main work sites along the project route. You may also notice intermittent test pit activity taking place on Southern Artery between Russell Park and Coddington Street. Please note that there will be no construction on Monday, September 5 in observance of Labor Day.

Manhole installation continues on Southern Artery between Greenleaf Street and Russell Park. Here contractors are excavating and installing the second of two manholes at this location. Please note that traffic will be maintained in both directions during construction. For more detail on the manhole installation traffic management plan for this work site, please click here.

Lastly, duct bank installation is scheduled to continue on Newport Avenue between Central Avenue and Morgan Road.

As always, we ask that drivers and pedestrians remain mindful of lane shifts, posted traffic signage, and the direction of police details stationed around these work zones.

For a closer look at the project route, please click here to view our online map.

Week of September 5: Construction Activity

-Duct bank installation on Newport Avenue between N. Central Avenue and Morgan Road

-Manhole installation on Southern Artery between Greenleaf Street and Russell Park

-Test pit activity on Southern Artery between Russell Park and Coddington Street


Week of September 12: Construction Activity

-Duct bank installation on Newport Avenue between Warren Avenue and Morgan Road

-Night Work (Monday-Thursday, 7:30PM - 5:30AM): Duct bank installation on Newport Avenue between Elmwood Avenue and Lincoln Avenue

-Manhole installation on Southern Artery between Russell Park and Coddington Street

Please know that construction is scheduled to minimize the impact on traffic and everyday life; sections of your street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.

For more information on North Quincy Cable Project, please call 1-800-358-3879 or email a member of our team at info@northquincycableproject.com. You can also use the “Contact Us” page of our website to submit any questions, comments, or concerns.

Thank you,

The North Quincy Cable Project

*Please note, due to the complexities of outdoor construction, schedule is subject to change.