Latest Project Updates

04.07.2023

Project Update: April 7, 2023

Next week you can expect to see construction activity at three work sites along the cable project route. Please the bullets below for details.

Read more

03.31.2023

Project Update: March 31, 2023

Next week, barring inclement weather, you can expect to see continued excavation and duct bank installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.

Read more

03.24.2023

Project Update: March 24, 2023

Next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.

Read more

03.17.2023

Project Update: March 17, 2023

Next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.

Read more

03.02.2023

Project Update: March 3, 2023

Moving into next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation continues at our work sites on Furnace Brook Parkway. Please note that there is approximately two weeks of construction remaining on Furnace Brook Parkway.

Read more

02.24.2023

Project Update: February 24, 2023

Moving into next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation continues at our work sites on Furnace Brook Parkway.

Read more

02.10.2023

Project Update: February 10, 2023

Next week duct bank excavation and installation continues at our work sites on Furnace Brook Parkway.

Read more

02.03.2023

Project Update: February 3, 2023

Next week duct bank excavation and installation continues at our work sites on Furnace Brook Parkway and Field Street / Morrison Street.

Read more

01.27.2023

Project Update: January 27, 2023

Next week you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway and on Field Street moving in the direction of Morrison Street.

Read more

01.20.2023

Project Update: January 20, 2023

Next week you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Newport Avenue and near the intersection of Field Street and Morrison Street.

Read more