Project Update: April 7, 2023
Next week you can expect to see construction activity at three work sites along the cable project route. Please the bullets below for details.
Read moreProject Update: March 31, 2023
Next week, barring inclement weather, you can expect to see continued excavation and duct bank installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.
Read moreProject Update: March 24, 2023
Next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.
Read moreProject Update: March 17, 2023
Next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Morrison Street and Newport Avenue.
Read moreProject Update: March 3, 2023
Moving into next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation continues at our work sites on Furnace Brook Parkway. Please note that there is approximately two weeks of construction remaining on Furnace Brook Parkway.
Read moreProject Update: February 24, 2023
Moving into next week, barring inclement weather and extreme cold, you can expect to see continued duct bank excavation and installation continues at our work sites on Furnace Brook Parkway.
Read moreProject Update: February 10, 2023
Next week duct bank excavation and installation continues at our work sites on Furnace Brook Parkway.
Read moreProject Update: February 3, 2023
Next week duct bank excavation and installation continues at our work sites on Furnace Brook Parkway and Field Street / Morrison Street.
Read moreProject Update: January 27, 2023
Next week you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway and on Field Street moving in the direction of Morrison Street.
Read moreProject Update: January 20, 2023
Next week you can expect to see continued duct bank excavation and installation at our work sites on Furnace Brook Parkway, Newport Avenue and near the intersection of Field Street and Morrison Street.
Read more