Latest Project Updates

09.16.2022

Project Update: September 16, 2022

Next week you can expect to see construction activity at two main work sites on Newport Avenue (between S. Central Avenue and Morgan Road and between Beale Street and Brook Avenue).

Read more

09.09.2022

Project Update: September 9, 2022

Next week you can expect to see construction activity at two main work sites along the project route – Southern Artery between Russell Park and Coddington Street and Newport Avenue between Warren Avenue and Morgan Road.

Read more

09.02.2022

Project Update: September 2, 2022

This week you can expect to see continued activity at two main work sites along the project route. You may also notice intermittent test pit activity taking place on Southern Artery between Russell Park and Coddington Street. Please note that there will be no construction on Monday, September 5 in observance of Labor Day.

Read more

08.29.2022

Project Update: August 26, 2022

Next week you can expect to see continued activity at three work sites along the project route.

Read more

08.22.2022

Project Update: August 19, 2022

Next week you can expect to see continued activity from three construction crews. Two of these crews will continue duct bank installation on Newport Avenue between N. Central Avenue and Morgan Road. The third a crew will continue its manhole installation work on Furnace Brook Parkway between Hancock Street and Merrymount Parkway.

Read more

08.12.2022

Project Update: August 12, 2022

Next week you can expect to see activity from three construction crews. Two crews will be located on Newport Avenue between N. Central Avenue and Morgan Road (duct bank installation), and the remaining crew will continue its work on Furnace Brook Parkway between Hancock Street and Merrymount Parkway (manhole installation).

Read more

08.05.2022

Project Update: August 5, 2022

Next week you can expect to see construction activity at two locations along the project route: Newport Avenue between Morgan Road and Lincoln Avenue (duct bank installation); and Furnace Brook Parkway between Hancock Street and Merrymount Parkway (manhole installation).

Read more

07.29.2022

Project Update: July 29, 2022

Next week you can expect to see continued construction activity at three locations along the project route: Newport Avenue between W. Squantum Street and Wilson Avenue; Newport Avenue between Lincoln Avenue and Warren Avenue/S. Central Avenue; and Furnace Brook Parkway between Hancock Street and Merrymount Parkway.

Read more

07.22.2022

Project Update: June 22, 2022

Next week you can expect to see continued construction activity on Newport Avenue between George Road and Morgan Road as crews work to install the last manhole at this work site.

Read more

07.15.2022

Project Update: July 15, 2022

Next week you can expect to see continued construction activity on Newport Avenue between West Squantum Street and Wilson Avenue.

Additionally, excavation for manhole installation on Newport Avenue (between George Road and Morgan Road) is scheduled to begin.

Read more